          The step of changing the mold for everyone to put summed up:

    After the first device mold is disassembled mold, the first mold box and the die to rise to hook location bite the hook, and then drop the mold box, when the mold box fell to the bottom stop, will be placed on a pallet mold box, then The mold box rise, the pressure on until the die head and mold box wooden pallet stop after contact, then the die to the die block full release Remove screw connection block, and then start releasing the motor, then die and mold box while falling, to be down to the bottom stop, lift will die down.
         Secondly, the mold box raised 200mm to stop, and then the bottom of the mold box full pad pallet, remove the fixed mold box four bolts, start stripping machine, the mold box shoe drop to the bottom, then the mold and the mold box box slide from the mold box carried away. After it is small cement brick mold replacement is installed, first slide down to the very bottom of the mold box, put three pallets on the vibration platform, and then carried to the mold box mold box slider, start lifting motor until the mold box mold box when the slider along with increased exposure stopped, the mold along with four stop pole wire spring, with a stop pole bolted to the mold box slider away vibrating table wood pallets, start lifting motor, After the die and the die block light contact, stops rising, with the coupling block will die and die slide loose coupling, start lifting motor (reversible), mold me fall, backing out of the wooden box after molding , then start lifting motor until the die pressure head down into the mold box catchy with this level, stops rising, vibration 3 ~ 5S stop the launch, the module connector block with bolts tightened, and then start the lift motor, observe the mold box between the die and die and whether there is friction jamming phenomenon, if necessary to promptly adjust up and down freely between the tank and the mold until the die so far. In fact, very simple to operate, as long as the first successful replacement later buy new cement brick mold, to worry about not replaced.
       Shandong Shengya Machinery Co., Ltd. has been committed cement products machinery development, production and sale of advanced equipment, superb technical expertise and two decades of experience, the company has always been at the forefront of research and development center block molding machine market development Follow the advanced technology at home and abroad, to develop products for different investment needs of users, mainly block making machine, hydraulic tile machine, cement pipe machine, mixer, hanging roller machine, telephone poles machine equipment. At present the country with 19 offices and six overseas plants (Nigeria, Tanzania, Algeria, Kenya, Mozambique, Ethiopia) and exported more than 100 countries and regions.


    Previous: 没有了

    Next: 没有了

    < a href=" ">在线客服